PAST ABSTRACTS

Abstracts from SPT 2023

  • Authors: Toby Bird, Principal Engineer, Subsea 7 - Paul Westwood, Principal Engineer, ROSEN - Frank Bijster, Senior Sales Manager – North Western Europe & Israel, ROSEN

    This paper will present how a flowline and topsides have been designed to reduce CAPEX costs to while ensuring the safety and integrity monitoring of the flowline based on material selection. Subsea infrastructure, and in particular pipelines, need to be carefully evaluated for throughput piggability point of view. This is to ensure that the pipeline will satisfy the regulatory requirements for integrity monitoring. With deeper wells come higher pressures and temperatures, which often leads to exotic material selections with increased wall thicknesses and therefore higher project cost. Minimising CAPEX is repeatedly the aim of the pipeline design team whilst ensuring safety is maintained throughout the pipelines design life. Located in the Norwegian North Sea, the unmanned Fenris platform is approximately 50 km north of the Valhall field centre and has shut in wellhead conditions of 862 bar and 170°C. The pipeline system has been designed in 2 sections that complies with the DNV guidance for HIPPS protected pipelines. This was achieved by very close collaboration between the pipeline EPCI contractor, Subsea 7, and the proposed In line Inspection provider, ROSEN. The removal of the valves and PLR connections from the Fenris platform resulted in a major cost and weight saving for the platform design. This pipeline design also totally removed the need for personnel to access the unmanned Fenris platform for pipeline inspection operations on the 50 km carbon steel pipeline.

  • Authors: Aurelien Damour, Edgar Morishita Maeda and Emmanuel PEREZ, ITP Interpipe

    An operator in West Africa has requested ITP to improve its field-proven rapid J-lay Pipe-in-Pipe (PiP) for temperatures higher than 100°C or even 125°C. Currently, ITP Interpipe’s offshore field jointing system for PiP (more than 400km already in operation in West Africa and North Sea), uses a fast-curing polyurethane resin for load transfer across the field weld during J- or S-lay installation. This resin has the benefits of being a fast-curing material that will have little impact on the barge laying rate (3.5km/day achieved installation rate) but it has a limitation in term of design temperature in sea environment.

    To increase the capacity of this field-proven field jointing system, an alternate design is under qualification using a fast-curing grout specifically developed for this application. The use of a grout as several advantages compared to a resin: its Young’s modulus is more 10 times higher than polyurethane resin, and stable over the temperature windows from 4°C to 125°C. Also, the grout thermal expansion coefficient is similar to the steel thermal expansion coefficient resulting in limited thermal stress in the field joint in operation. This paper presents the progress of the qualification of this upgraded field-joint system. The first step of the qualification

    was to develop a grout formulation to fulfill the technical requirements of the load-transfer material: curing time of ~5min, intrinsic mechanical properties suitable with installation and operation loads. The new material was tested following standardized grout testings to confirm its ageing properties. In parallel, prototypes were fabricated and tested to confirm mechanical behavior of the grout under high bending strain (up to 0.4%) and with alternate traction/compression cycles. Another important part of the qualification is to develop a process and associated equipment for mixing and injecting the grout on the laying barge offshore. The main challenge is the grout curing time that excludes most of the standard grout mixing and pumping process: the operational risk is too high to pump the grout already accelerated, therefore a configuration has been developed with the grout accelerator being mixed after the pump. The paper will present the status of the qualification with the results of tests already done and the remaining technical uncertainties to be covered.

  • Authors: Antoine Marret, Piotr Malota and Torgeir Helland, TechnipFMC

    The Fenja Field is located offshore mid-Norway at a water depth of approximately 324 m, and consists of two separate hydrocarbon accumulations, the Pil and Bue reservoirs. The reservoirs’ fluid properties are challenging, and Neptune Energy concluded that the Electrically Trace Heated Pipe-in-Pipe (ETH PIP) Technology would be the best technical and economical option to develop and produce the reservoirs. This paper presents a high-level overview and outcome of the development, industrialization, fabrication and installation of the TechnipFMC’s second generation ETH-PiP for application to the FENJA field development. It also presents the outcomes from the ETH system performance test conducted during the final commissioning of the system. The new ETH-PIP v2.0 has higher electrical rating of 3.8/6.6kV to overcome the specificities of the FENJA field development including the long tie-back distance of 38km which makes FENJA the longest (and largest) ETH-PiP in the world. The installation was finalized in Summer 2021, with the complete system being connected and tested from the Njord A platform after it returned from refurbishment in Spring 2022. Final commissioning and validation of the ETH-PiP performances were completed early 2023.

  • Authors: Tiago Kaspary, Eduardo Menezes, Jessica Pisano and Paul Montague, Cladtek

    Mechanically lined pipe has been a very competitive alternative to solid CRA pipe or metallurgically clad pipe for offshore and onshore pipelines conveying corrosive fluids, with decades of successful application. Cladtek´s innovative solution of cladding and machining the pipe-ends back in 2004 significantly improved MLP installability by addressing the associated challenge of fit-up with clad girth welds, having become the industry standard. In the years since, Cladtek has created a number of improvements to the product, including the fabrication and installation of the largest diameter MLP in offshore use in Nigeria and the fully lined rigid risers in the Brazilian Pre-Salt. In this paper, Cladtek discusses the history of its MLP in the industry, its understanding on the limits of its application - in particular through case studies and improvements in recent projects, addresses a number of ongoing developments in the fabrication and inspection of this product. Finally, opportunities for new developments are proposed.

  • Authors: Chas Spradbery, Peritus International Ltd and Terry Griffiths, Aurora Offshore Engineering

    It is well understood that traditional on-bottom stability designs are over-conservative for small diameter items such as cables and umbilicals. Furthermore, that when cables are placed on rough or rocky seabeds the traditional methods do not adequately capture the interactions between the cable and the seabed. Therefore, a new approach to cable stability on rocky seabeds has been developed. This approach is contained within a new British standard BSI 10009, due to be published later this year. This presentation will cover the background research leading to the novel approach to seabed stability described within the standard, along with case studies demonstrating how the methodology as been applied in real world situations leading to both cost and risk reductions.

  • Authors: Dr. Chen Shen, Mamadou Ahmed-Kogri, Dr. Eric Giry, Richard Stableford and Dr. Diego Pavone, Offshore Subsea Engineering, Saipem

    Reel-laying is a long-established method for installing rigid subsea pipelines and has an extensive global track-record. In comparison with J or S-Lay methods, reel-laying imposes large deformations which could trigger failure by buckling, fatigue or fracture. Pipe manufacture and pipeline fabrication are carefully controlled, but each pipe has a tolerance on geometry and materials properties. Saipem performed a programme of full-scale reeling simulations to develop an accurate computational model for use in reeled pipeline design. The reeling simulations included 12m long pipes cut in half with an accurate counterbore machined in one end before welding back together. This creates a union of carefully controlled strong and weak “mismatched” pipes. Materials testing was also performed. FE simulations using parameter-based material model was validated against the full-scale test data. The FE modelling allows the DNV “pipe mismatch failure curve” to be developed into a useful tool in the Pipeline Design Engineers toolkit.

  • Authors: M. Cerulli, M. Abdullayev, C. Cooper, TechnipFMC - Jonathan Stuart Bracher, Equinor and Pål Foss IKM

    The Residual Curvature Method (RCM) has proven to be a very effective method to initiate controlled lateral buckling of exposed pipelines that are installed using reel lay vessels. Most pipelines installed to date that have adopted RCM buckle initiators were single pipelines. However, as the technique has gained maturity, it has started to be used for Pipe-in-Pipe (PIP) flowlines as well. This paper presents a summary of the work undertaken to demonstrate the suitability of RCM for the Equinor Kristin Sor PIP system, which is exposed to trawl interaction and where RCM buckle initiators were adopted to control lateral buckling. Key aspects of the interfaces between in-place design and installation engineering will be presented with particular attention paid to the uncertainties that need to be addressed to demonstrate the robustness of the solution. Along with the usual uncertainties considered in pipeline lateral buckling analyses, for example pipe soil interaction and bottom tension, other uncertainties specific to RCM installation are examined, including RC strains, curvature and RCM section rotation. The results of the assessment are presented, key challenges are discussed and lessons learned shared.

  • Authors: Leif Collberg, Jan Fredrik Helgaker and Erling Østby, DNV

    Hydrogen gas as an energy carrier is predicted to play a key role in the global efforts to decarbonize. As part of the hydrogen value chain, pipelines are considered an attractive option for transportation, either for transportation of pure hydrogen gas or as a mixture with natural gas. In this context, both new pipelines and utilisation of existing infrastructure (re-qualification) are possible options. One contributing factor for the push on hydrogen pipelines it its potential ability to accumulate/store gas which is a very tempting aspect when connected to non-stationary generation like solar and wind. One interesting question arise; is there a need for any R&D for hydrogen pipelines with all the statements of “hydrogen ready” pipelines? In the on-going DNV JIP H2Pipe, a design level scheme has been proposed to differentiate designs depending on its maturity and knowledge ranging from low to very high. Today, DNV consider only the level Low, typically covered by AS;ME B31.12, to be sufficiently proven for design which excludes the majority of offshore pipelines. The design levels and the linked concerns will be presented. A discussion of concerns will also be given and the difference between “do not know/lack knowledge” and “not possible”.

  • Author: Colin McKinnon, Technical Director – Technical Consulting, Wood

    • Code and regulation requirements for H2 service

    • Operational safety risks and mitigations: hazardous areas, vapour cloud explosion, ESD, risk contours

    • Emergency response: shut down and venting

    • Hydrogen operations: SCADA, leak detection, visual inspection, testing

    • Hydrogen integrity management: pigging, crack detection, repair

  • Authors: Kenneth Solbjør, Product Manager, Oceaneering - Gary Anderson, Senior Manager Sales, TD Williamson - Georg Johnsen, Principal Engineer, Equinor

    Remotely operated vehicles (ROV) and support vessels are essential to support subsea pipeline operations, including subsea inline isolations. Subsea pipeline isolation operations require robust communication systems to control and monitor tool loading, tracking, activation and deactivation. Typically, the system is hardwired or acoustically linked to the platform or vessel, supported by the vessel ROV. The duration of the isolation will dictate the support vessel time on location. Advancements in remote communication technology in both the ROV industry and the pipeline isolation industry have shown how support vessel dependency in such operations can be eliminated. This paper covers an actual pipeline decommissioning project whilst keeping the downstream pipeline system operational, all remotely from an onshore location. The solution paired advanced pipeline isolation technologies with a resident, battery-powered, work-class E-ROV system with LTE connectivity. The combination enabled the subsea inline isolation to be performed via a remotely deployed EROV system from an onshore operations center, an industry first. By using the onshore remote operations center, the project team was able to collaborate, control and watch live operations through the remote EROV. The isolation tool communication system interfaced through the EROV allowing the tracking, activation, monitoring and unsetting of the tool subsea, direct from the onshore operations center. Removing the vessel requirement eliminated costs, improved safety and dramatically reduced the CO2 and environmental footprint of the isolation operation.

  • Authors: Suzaini Zainal Abidin, Helmi Ngadiman and Faizal Shahudin, PETRONAS

    This paper summarizes the basic operational steps taken by PETRONAS to complete its first open sea to open sea offshore Horizontal Directional Drilling (HDD) at one of its pipeline crossing locations at KP 83.709 for its newly installed pipeline for project located at Java Sea, Surabaya, Republic of Indonesia. The pipeline is a 12-inch, 110-kilometer gas export pipeline from the “A” platform to Onshore Receiving Facilities (ORF), at a water depth of 5 to 6 metres below mean sea level (MSL). This paper describes in general the construction methodology and operational steps for using the HDD method to cross beneath the 18-inch buried live existing pipeline from open sea to open sea. To comply with the authority regulation, all pipelines located less than 13 metres below sea level and within shipping channels must be buried at a depth of two metres below the seabed, this HDD method was chosen instead of the typical subsea pipeline slipper crossing. The crossing has been carried out in a single drilled section measuring approximately 350 metres in length from the entry point (at Drill Barge, Barge #1) to the exit point (at Receiving Barge, Barge #2) located offshore. The clearance requirement for the existing 18" pipeline (buried 2 metres below seabed) is between eight (8) and ten (10) metres below the pipeline's bottom. The entire drill string length is approximately 610 meter including a 130-meter-long tail string coated pipes with 30mm thick concrete (at both side) which was pulled and laid on the seabed before Pipe lay Barge came to pick-up, tie-in and continue laying towards onshore. Despite numerous challenges and limited experience, the project was completed on time, within budget, and with no LTIF or TRCF. This paper will provide a guideline for future similar project undertakings on the selection of marine vessels and equipment, the overall safe operation, and the efficient method to execute the project successfully. Commonly, the HDD operation is performed on the land side for pipeline shore approaches or pipeline crossing purposes to avoid an open-cut method across any existing facilities/utilities (road crossing, building, river etc). However, in this project, the HDD operation was performed at the open sea crossing the existing oil pipeline.

  • Authors: Jean Malnory, DNV - Odd Reidar W. Boye, IKM Testing AS - Stein Rimestad, Equinor 

    The BM-C-33 gas export pipeline (GEP) is one of the deepest large-OD pipelines under development. The offshore field is located 200 km off the Brazilian coast, in 2800 m water depth in the southern part of Campos basin. It was early identified that water filling, system pressure testing (SPT) and subsequent dewatering would become operationally challenging and also have a significant cost impact.

    The BM-C-33 project team has therefore with support from DNV assessed the opportunity for obtaining an equal - or better - integrity level without performing SPT for its GEP. The project has adopted the methodology developed as part of the Replace JIP and the resulting guideline issued in 2020. The JIP REPLACE guideline is based on DNV-ST-F101 allowing replacement of the SPT of a pipeline system with alternative means while keeping an equal or better safety level.

    This paper will present the REPLACE methodology adopted by the project; more specifically, what were the motivations for BM-C-33 and the implementation process - including checking consequences of the system design and the added safeguards through a semi-quantitative risk assessment. This semi quantitative risk assessment demonstrates that these proposed safeguards ensure an equivalent or better safety level.

    Development of the Pre-commissioning (PCO) Philosophy for BM-C-33 will thereafter be presented, outlining essential conditions, assessments and specific solutions implemented to conform with the REPLACE guideline. A comparison with a conventional PCO solution will further be made, identifying the main upsides with REPLACE for BM-C-33

    In total, the paper highlights how the REPLACE methodology can represent a potential gamechanger for certain projects. The new methodology offers significant advantages particularly for large-OD, long and deep pipeline systems. Avoiding water filling may provide a long range of upsides with regards to offshore operations, environmental impacts (chemical usage), equipment spreads and in-field logistics.

  • Authors: Svein Are Løtveit, Senior Advisor and Founder, 4Subsea and Morten Eriksen, Senior Advisor, 4Subsea - Arne Dugstad, Chief Scientist, Institute for Energy Technology

    This paper presents a best practice for corrosion assessment of flexible pipes. The best practice is based on the two flexible pipe corrosion monitoring (FPCM) projects. The objective was to understand the annulus chemistry and the corrosion mechanisms and to give best practice guidance to integrity assessment and monitoring. The FPCM-II project included the following partners: 4Subsea, Project management - A/S Norske Shell, Okea AS, Equinor ASA and Chevron U.S.A. Inc, Industry sponsors - Institute for Energy Technology (IFE), R&D partner.

    Corrosion of the steel armour wires is one of the most important mechanisms limiting the safe service life of flexible pipes. In an oxygen-free annulus with water present, confinement combined with large steel areas and low water volumes normally leads to very low corrosion rates. In some upset conditions, the corrosion rate may be high, and the best practice gives guidance for evaluation of these. The FPCM II Best Practice also considers various corrosion scenarios, supporting tools, evaluation methods and topics relevant to risk evaluation.

  • Authors: Danny Krogh Nissen, Technical Manager, Development and Qualification, NOV Flexibles Denmark and Kasper Lund, Metallurgist, Materials and Testing, NOV Flexibles Denmark

    When operating in high CO2 applications, unbonded flexible pipes reinforced by conventional carbon steel are exposed to the risk of stress corrosion cracking (SCC), resulting in integrity failure, or significant service life reduction. This is relevant for conventional offshore O&G production and the emerging field of carbon capture, utilization, and storage (CCUS). The corrosion resistant flexible pipe provides an extension to the safe zone on conventional flexible pipes by eliminating the SCC risk and securing full-service life, while in all other aspects behaving as a conventional flexible pipe. The objective of this paper is to present the qualification evidence for flexible pipes with a highly corrosion resistant, high strength steel grade replacing the carbon steel armour wires with identical wire profiles and verifying the use of consolidated flexible pipe methodologies and processes. An extensive risk assessment has been performed, resulting in +65 individual identified threats, endorsed by Independent Verification Agency, covering dynamic HPHT deep water applications. A substantial amount of material qualification has been performed, showing suitability within; CO2 stress corrosion cracking, sulfide stress cracking (SSC), crevice corrosion and hydrogen embrittlement, pitting resistance, biocorrosion, and much more. A complete prototype pipe has been manufactured, and full-scale tests have been successfully performed, showing excellent compatibility with existing manufacturing processes and design methodologies. This paper will present the outcome of the FMEA sessions, summarizing the outcome of 5 separate qualification plans leading to full-scale product validation.

  • Authors: Barry Marshall, General Manager and Jan Stander, Managing Director, Aisus

    The energy industry has for many years been seeking solutions to the complexities of integrity management of pipeline assets. Unbonded flexible risers have been a particular difficulty, and the introduction of fully bonded composites creates new challenges for integrity management. Until now, the lack of a practical and effective inspection method has forced integrity management to be based on engineering models and statistical predictions using extremely limited inspection data. Inspection data from a small sample area of a pipe system has had to be assumed to be representative of the overall pipe condition for integrity management. The data is used to predict the overall condition as well as the life expectancy of full complex pipeline networks, by statistical analysis rather than actual evidence. Additionally, new pipe designs and complex pipe structure such as Unbonded Flexible Pipe and Thermoplastic Composite Pipe (TCP) have been introduced to the market. These have essentially been ignored for inspection because regulators have deemed them un-inspectable, as no technology existed to inspect these new pipes due to their multi-layered complex constructions of non-metallics. This white paper explores how new high-speed x-ray technology is transforming the industry, making it possible for the first time to scan the full length of spoolable pipes while providing almost microscopic-level insights. This enables manufacturers to provide greater assurances and quality control to clients and gives operators a traceable digital record for the full lifecycle of the pipeline. Any changes to the pipe condition can be detected and monitored, providing data that gives confidence in the life of asset predictions, as well as enabling feedback to designers, manufacturers, and regulators. The end result is a dramatic reduction in Risk and an elimination of in-field failures.

  • Authors: Gilles Gardner and Adam Armstrong, The Impulse Group

    Topside end fittings of unbonded flexible risers are designed with annulus vent ports that serve two purposes; to safely vent permeated annulus gases and to allow integrity testing of the outer sheath. If these vent ports become blocked, annulus testing cannot be carried out and the build-up of gas has potential to rupture the outer sheath allowing seawater to flood the annulus resulting in corrosion of the structural steel components of the riser.

    The Impulse Group has developed a method of inspection which utilises a small diameter articulating camera system that can be manipulated to travel through the annulus vent port tubing providing valuable insight into its condition. This method allows the full inspection of the vent port tubing to identify any debris or tube compression preventing gas release, allowing The Impulse Group to consider methods of repair to any blocked ports and re-establish a topside connection either by mechanical means or simply utilising a vacuum attachment. Application of various external fixtures also makes it possible to articulate the camera to the end of the vent port to inspect for localised corrosion of structural wires within the end fitting region resulting in detection of cracking and corrosion within the riser structural layers.

    This paper describes the development and offshore deployment of the annulus vent port camera inspection system, cleaning of the vent port tubing and presents sample findings.

  • Authors: Ismael Ripoll, Xodus Group - Carlos Sicilia and Emilien Bonnet, TotalEnergies

    Operation at temperature and pressure of exposed subsea pipelines results in effective axial forces which may cause lateral buckling. To perform the lateral buckling design, the subsea pipeline industry typically uses a combination of Monte-Carlo simulations and finite element analysis (FEA). The Monte-Carlo simulations are used to determine the longest virtual anchor spacing that can be reliably guaranteed (characteristic VAS), and FEA is used to determine the longest VAS with acceptable mechanical conditions (tolerable VAS). The lateral buckling design then needs to ensure that the characteristic is less than the tolerable VAS. In this context, this paper presents a Monte-Carlo algorithm which determines the soil friction distributions conditional to buckling, and then an approach in which the tolerable VAS is in turn determined using these conditional soil friction distributions. For pipelines in which the soil friction distributions provided by the geotechnical specialists do not always lead to buckling, the proposed approach may have a significant impact on the overall lateral buckling design.

  • Authors: Chris Cooper and Piotr Krawczyk, TechnipFMC

    Engineers have been calculating the wall thickness of pipelines for years. It is often one of the first tasks to be undertaken in the design process and the initial calculation for pipe wall sizing to protect against the burst limit state is often considered to be one of the most straight forward tasks. DNV-ST-F101 provides an easy-to-use analytical equation to determine the burst resistance. However, it also includes a clause, which until very recently, has not been widely understood and therefore, rarely used in pipeline design. This clause requires the engineer to consider the effect of compressive true wall force on the burst resistance. Applying this clause is far from straight forward and has been the subject of considerable debate on a few recent projects. This paper provides an overview of the problem, before summarising an approach that may be adopted to address this code requirement. A few case studies are presented, and some practical implications discussed.

Abstracts from SPT 2022

  • Authors: Neil Agnew, Technical Support Manager – Pipeline Services and Peter Dixon, Regional Engineering Manager – Europe, Africa, Russia and Caspian, Baker Hughes Process and Pipeline Services

    Baker Hughes Process and Pipelines Services (PPS) successfully completed the pre-commissioning campaign for Subsea 7 on the Tamar Southwest Project in the Levantine Basin in 2020. The Levantine Basin is located in the easternmost part of the Mediterranean Sea off the coast of Israel. Two pipelines, 10” and 16”, laying approximately 1,670m (5,479ft) below the surface and running a combined 17.4km (11.4 miles) were flooded, cleaned, gauged, hydrotested and dewatered. The pre-commissioning scope of work was split across two campaigns. Both campaigns involved novel concepts which proved to be successful and instrumental in the completion of the fast-track project. Firstly, the pipeline flooding, pigging, cleaning, gauging and hydrotesting were performed from the remote deepwater location with the Baker Hughes Denizen™ Subsea Pre-Commissioning unit. This iteration of the technology allowed for a faster and more robust hydraulic integration between the client’s remotely operated vehicle (ROV) and the Denizen system. Subsequently the pipelines were dewatered via a bespoke coiled tubing downline system with over-boarding platform. The vessel-based high-pressure air/nitrogen compression spread was double-stacked to reduce the footprint on deck. However, this generated significant engineering challenges regarding access and heat dispersion. Diligent engineering and yard trial phases by PPS allowed the challenges to be overcome off of the critical path and yielded a successful, fast-track, offshore campaign.

  • Author: Matthew Lloyd, Saipem Limited

    Case studies are presented for detrimental torsional effects interfering with offshore installation operations. These include a flexible flowline installed to water depths exceeding 900m via a centrally positioned VLS and 14ʺ rigid flowline installed via S-lay to 500m water depth. Both challenges required different innovative solutions to find timely and cost-effective solutions within the offshore campaigns. Residual torsion in a reeled flexible, which had been stored for a significant time, impacted the first end termination landing onto seabed infrastructure. The challenge of operating in deep water is that any corrective alignment occurs vertically from above, as opposed to the more desirable lateral directions. An anti-rotation buoy pre-installed onto the 14ʺ flowline (500m from the head) collapsed, and the flowline rotated 90°, measured from the pipeline end. The rotation was observed to be induced gradually along 1.8km of flowline length. The flowline was to be recovered in a J-lay configuration, fitted with a termination assembly and laid down again. Therefore, to meet with the welding tolerances, the flowline rotation had to be mitigated prior to reaching the vessel hang-off platform. The paper highlights approaches for overcoming some of the issues presented in the scenarios and outlines the actions taken offshore.

  • Ed Pratt, Senior Rigid Pipeline Development Engineer, TechnipFMC

    Plastic Lined Pipe (PLP), where a carbon steel (CS) host is lined with a polymer for corrosion protection, has been installed using the reel-lay method for subsea Water Injection (WI) applications by TechnipFMC for more than 25 years. As industry demand has grown for WI at high pressures, the global supply chain has tightened, resulting in price increases for corrosion resistant alloys. Using commodity polymers, PLP becomes an increasingly cost attractive solution. An improved, robust connection method is required to increase the operational range of this technology to high pressures, and alternate uses such as production fluids, H2 and CO2 transport and storage. A new press-fit connector technology has been developed per DNV-RP-A203 guidelines, with continuous DNV involvement. This method of qualification has delivered a reduction in time to certification of new technology, with feedback from the certifying body provided throughout, to reach DNV TRL5 endorsement. Qualification testing consisted of assembly of full-scale prototypes followed by exposure to life-cycle loading including; hydrotesting, reeling simulation, accelerated ageing with combined shutdown cycles, and fatigue cycles for dynamic applications. Further, connectors were tested for creep and cyclic loading. The press-fit technology was found suitable for high pressure, dynamic riser service and also low cycle service with lateral buckling, such as in high pressure/temperature injection systems. Following this success, the technology is compatible and may be used with other TechnipFMC developments in PLP technology, including hydrocarbon transport and future H2 and CO2 transportation.

  • Authors: Nikolaos Chatzimanolis, Gianluca Colonnelli, Pasupathy Ragupathy and David Kay, Subsea 7

    This paper presents the method employed for carrying out Upheaval Buckling (UHB) FEA accounting for the effects of slurry on the pipeline response. In order to accurately capture the pipeline’s global post buckling response and minimise the cover requirement, the analysis accounted for the actual slurry layer thickness as it varied along the trench. A 4" MEG pipeline was trenched and buried along its route in water depths less than 350m for protection from fishing activities. The pipeline was trenched using jetting followed by eduction of fluidised soil and buried with crushed rock. A slurry layer of varying thickness settled over the pipeline after trenching as complete eduction was not possible at this site. The crushed rock was placed over this slurry layer and the pipeline. The level of penetration of the crushed rock into the slurry layer could not be reliably determined soon after the placement, when the cover requirement needed to be determined. With respect to UHB, the worst-case scenario considers that the crushed rock doesn’t penetrate the slurry layer whereas the pipeline can move upwards through the slurry layer with no resistance until it reaches the rock layer. This allows the pipeline's curvature to increase locally at locations where there is slurry and consequently the tendency and potential for UHB increases. Therefore, the downforce which is required to restrain the pipeline and the associated cover requirement increase due to slurry. The thicker and more uneven nature of the slurry layer, the more amplified its effect is.

  • Authors: Linlin Jiao, Principal Engineer and Kjetil Bergseng, Principal Engineer, DNV

    Free spans on subsea pipelines develop due to various reasons, e.g., seabed unevenness, scouring, installation of artificial supports, crossing and end terminations, etc. Free spanning of subsea pipeline is a typical concern for pipeline integrity with respect to fatigue and local buckling (ULS) capacity. The fatigue herein is mainly induced by dynamic environmental loads due to Vortex Induced Vibration (VIV) and direct wave. The onset of VIV depends on the characteristics of spans, e.g., span length and gap. The span lengths are thus required to be monitored regularly and limited within design criteria. The widely used free span assessment method in industry is still a manual processing, going from simple screening criteria through to advanced calculations for each critical span configuration. Recently, DNV has developed an automated (digital) model for free span assessments which assesses the fatigue damage per KP location along the entire pipe. The advancements in data storage and processing supports automatically accounting for multi-span interactions and changes in free span configurations within entire survey history. So far more than 50 subsea pipelines have been assessed by DNV applying this digital model. This paper introduces the theory background of fatigue assessment in accordance with recommended practice DNV-RP-F105 Free spanning pipelines, outlines the application of digital free span assessment method in pipeline integrity management work, and presents the relevant fatigue results of two representative pipeline cases.

  • Authors: Kristen Andrew Foshaug, CTO and Nitin Patel, CSO, Connector Subsea Solutions

    Anchor and holdback clamps are specifically designed to grip onto the pipeline to retain its movement and prevent pipeline walking, which left unchecked can cause cumulative axial displacement leading to potential failures at tie-ins or risers.

    Traditional methods require the coating to be removed to enable a structural interface with the bare pipe. However, removing pipe coating and interfacing with the bare pipe in typical deepwater applications can carry significant risks associated with cold spots and corrosion, in addition to the challenge of removing coating in a deepwater environment.

    This paper describes a clamp solution that grips directly onto the pipeline coating, dealing with challenges of creep of the thermal insulation as well as thermal expansion/contraction during operation cycles.

    Features included in the CSS clamp solution

    • Radial creep compensation allowing a high load input and catering for thermal expansion/contraction
    • HISC and corrosion protection of springs
    • High degree of coating confinement leading to optimized coating behaviour
    • Radial activation of gripping
    • Precise load control of gripping force to avoid local collapse of the pipeline and overstressing the coating
    • Possibility of in-service inspection to verify creep values during the clamp’s lifetime
    • Deepwater ROV-installable and retrievable

    An extensive full-scale test and qualification programme was performed to validate important principles of the solution. After successful completion of the test programme, the order of two permanent clamps was sanctioned. The two clamps were installed successfully at 830m water depth in December 2020

  • Authors: F. Örberg, C. Geertsen and G. Salque, ITP SA, France and V. Niesen, Evoleap, USA

    A joint venture between ITP-Interpipe and McConnell Dowell has recently performed an EPC project to design, fabricate and install a 1.8km-long subsea electrically heat-traced pipe-in-pipe (EHT PIP) pipeline connecting two refineries across a navigable marine channel in Southeast Asia. The pipeline will transport highly viscous bitumen and its EHT system can be used to reheat the fluid from ambient to its min. flow temperature or maintain it indefinitely at min. flow temperature in case of shutdown. The line is designed to a temperature of 228°C, the highest for a subsea pipeline to date. The author will provide feedback from the construction which required accurate staging of multiple onshore and offshore sequences, namely:
    • Onshore fabrication
    • Marine and civil works (performed in parallel)
    • Tie-in, pre-stress and commissioning operations

  • Authors: Callum Peace, Nick Waple, Harry Cotton, Luke Swan and Hooman Haghighi, Wood plc

    The drive for energy transition is currently underway, with many projects looking to convert or develop new facilities for integration into existing infrastructure. Governments are increasingly recognising hydrogen technologies as tools to meet decarbonisation goals. Hydrogen can be moved in a variety of forms, including as a pressurised gas, shipped in tankers as a cryogenic liquid at -253◦C, and in the form of hydrogen carriers such as liquid ammonia or methylcyclohexane-MCH. These options introduce unique challenges and obstacles to overcome to allow for practical and efficient transportation. Wood has conducted a review considering International pipeline codes/standards to determine their applicability to Hydrogen Service. One code, ASME B31.12, lists Hydrogen specific material requirements replated to hydrogen embrittlement, toughness degradation and increased fatigue crack growth rate of steel and is currently considered the governing code for H2 service. Case studies were undertaken for the repurposing of offshore natural gas pipelines for gaseous H2 service considering various levels of material qualification. Moreover, a range of flow modelling were carried out in order to compare the achievable energy flow/capacity of natural gas vs hydrogen (as energy carriers) for different scenarios by considering the design and operational constraints for such systems. This review also considers the readiness of the industry to provide pipeline technologies for the transportation of each hydrogen vector, including carbon steel qualification to ASME B31.12 and insulated pipe qualification for liquid hydrogen at cryogenic temperatures not seen within traditional hydrocarbons. Additionally, operational constraints and considerations associated with each option have been addressed.

  • Authors: T. Guegan and C. Geertsen, ITP SA, France and Supernode, Ireland

    Adjusting to climate change has led to an unprecedented push for replacing fossil fuel sources with renewable energies. Offshore windfarms will provide a significant proportion of that energy as wind conditions, safety and visual impact are more favourable offshore than onshore. Typical windfarms harness the power of several dozen wind turbines by transmitting the generated power to a single High Voltage transformer to increase the transmission voltage to several 100 kVs and exporting it to shore. The transformer and the export cable are often the costliest single ticket elements of such an offshore development, and with the increasing distance to shore of new developments, these costs increase. Superconducting transmission cables are an opportunity to either decrease those costs by transporting the power at lower voltage (and thus saving on the transformer units) or creating bulk transmission cables that funnel multi-GW power from several windfarms. Superconducting cables have been used industrially onshore for more than a decade but mostly in urban environments where their higher per-metre cost is offset by savings on real estate (narrow right-of-way, smaller/fewer transformers). Superconducting cables need to operate at a temperature of 77K/-196°C or less to be effective. This is achieved by installing the cable inside a double-walled pipeline (cryostat) that allows flowing liquid nitrogen (LN2) along the cable while minimizing heat ingress from the environment. Based on its technology for LNG, ITP has developed a thermomechanical design for a reeled, cryogenic pipe-in-pipe hosting superconducting power cables. A newly constructed high-precision cryogenic test bench validates the thermal performance. The author will present the design of the cryogenic envelope and key figures for its integration into a windfarm. Results obtained from a test campaign on a full-scale (8”/16”) cryogenic pipe-in-pipe provide the thermal and mechanical data to discuss the constructability of the system.

  • Authors: Didier Hanonge, TechnipFMC France / Jean Paul Ferraz and Romain Ferre, TechnipFMC Brazil

    CO₂-induced Stress Corrosion Cracking (CO₂-SCC) was reported by ANP (National Petroleum Agency - Brazil) in 2017 after the failure of a flexible riser operating in a severe CO₂ environment. This was a major challenge for operators in Brazil extensive pre-salt fields where flexible pipes have and will continue to play an important role. Since then, an extensive program has been executed providing a plethora of small and full scale test results. CO₂- SCC has been reproduced on all families of carbon steels, demonstrating the robustness of the test procedures. This major accomplishment allowed to build safe domains which have been certified. Those domains are defined by the maximum local stress acting on the wire and the CO₂ content, which are the main parameters, that can cause CO₂-SCC to initiate in presence of water. In addition, progress have been made in the modelling of the diffusion process of the gas species from the bore into the pipe annulus. The complexity of the flexible pipe annulus has been included in the diffusion methodology. New tools, allowing to precisely assess total local stresses on armour wires, considering the manufacturing process, were also developed. Risk assessment of pipes operating outside this SCC Free domain is addressed by a new and inventive methodology. This approach is based on dissection of pipes recovered from field and fracture mechanics theory and allows to evaluate the service life of those lines operating in severe conditions. The objective of this paper is to present the breakthrough progress in the CO₂-SCC understanding, allowing the safe design of flexible pipes against this new failure mode.

  • Authors: Asli Yazici, Senior Structural Engineer and Rahul Raghukumar, Senior Pipeline Engineer, IRM Systems
    Co-authors: Rutger Schouten, MD, IRM Systems and Ulrich Tiefes, Head of Pipeline Engineering, Wintershall Noordzee

    In the recent years, the need for continuing operations with aging assets has increased highly. The Operators are now looking for ways to use data effectively for optimizing pipeline operations to obtain more control over aging assets and support leaner operations in order to lower the operating costs.

    Wintershall Noordzee and IRM Systems jointly developed a risk-based inspection (RBI) methodology for offshore pipelines which overruled the conventional time-based inspection methodology. The risk-based inspection strategy was implemented on a digital platform indigenously developed by IRM Systems called PIBOT¹ to suit Wintershall Noordzee’s requirements. The capabilities of the digital platform were data analysis, degradation forecasting, integrity assessment, risk assessment, survey optimization and automated report generation.

    The risks assessment was performed based on a quantitative approach in accordance with the internationally recognised standards. The PoF² and CoF³ determination was automated by the software using decision trees, and their values were re-calculated when new inspection results were uploaded into the digital platform along with the updated operational data. The PIBOT calculates the risk profiles along the pipeline based on the Structural and Third-Party Threats, the results of which are presented on GIS System and linked to the Wintershall Noordzee Risk Matrix. The outcome is used to select the inspection intervals. The RBI implementation helps to increase the efficiency of data management/interpretation and provides the opportunity to focus on high-risk sections of the pipeline. Automating this process using PIBOT assures significant OPEX reduction for Wintershall Noordzee Asset Management.

  • Authors: Stephen Cater, Principal Project Leader, TWI Technology Centre and Santonu Ghosh, R&D Project Lead for Strategic Projects, Element Six UK Ltd

    Joining steel by welding is one of the crucial technologies in all fabrication, including subsea pipelines, and arc welding has long been the leading technology for that application. Recent advances made by Element Six in the development of new FSW tool materials are now allowing the transfer of the proven benefits of FSW to steel to begin. This paper outlines how the new generation of E6 tools allows consistently good welds to be made in a range of steels typical of those used in the pipeline sector. Initial work was performed to demonstrate that tools used for fabrication in 6mm thick carbon steels had a consistent and useful life of up to 60m of weld, and that the welds produced were defect free. The tools were then further developed to permit welds to be made, in a single pass, in steels up to 12mm thick, with the potential to move to greater thicknesses should the market demonstrate that need. In addition, work has demonstrated additional advantages the E6 PCBN tools bring to the friction stir welding process in steel, including the ability to:

    • Enhance the strength of the welds made
    • Join hard to weld grades, and to make dissimilar welds between carbon and stainless steels
    • Weld under water and in oil
    • Potentially enhance the fatigue life of existing structures by friction stir processing their existing arc welds
    • Use the friction stir processing technique to aid in rehabilitating pipelines for the transport of hydrogen & CO2.

  • Authors: Renaud Dessaint, Renaud Phelut and Mickael Guignon, TechnipFMC

    This paper aims to present an update of the cost effective and versatile smooth carcass technology development, the advanced carcass geometry that improves flow assurance performances and suppresses possible occurrence of Flow Induced Pulsation (FLIP). This paper reviews the smooth carcass principles and advantages, presents the thorough qualification including a full-scale dynamic test, certification achievements and growing manufacturing track record. Based on a FMECA, a qualification program, in compliance with API 17J & B, covers the whole life cycle of a flexible pipe. This is built jointly with the involvement of a third party that witnesses the whole process, confirming the robustness of the overall approach.

    Engineering, prototypes manufacturing and full-scale tests campaign validated successfully the static applications. For the qualification towards dynamic applications, a test program has been established on the basis of a gap analysis with respect to specificities introduced compared to conventional carcass. It resulted in performing medium, and full-scale dynamic test representative of dynamic field conditions. Certification is now achieved. Manufacturing track record includes today flexibles from 8 to 14in ID with austenitic and duplex materials of several sizes, over more than 20 km in total, beyond 1,000 meters water depth.

    This paper presents the final steps of qualification and certification for dynamic applications, jointly with the large envelop of manufacturing capability demonstrated through project delivery. It further substantiates the robustness of the smooth carcass technology enabling risers and flowlines to reach best-in-class flow assurance performances, while also preventing any risk of FLIP.

  • Authors: Alastair Walker, Advanced Mechanics & Engineering Pty, Ltd and Pieter Swart, SeaLeopard Engineering BV

    As part of the pipeline pre-commissioning, the objective of a system pressure test (a.k.a. Hydrotest) is to prove a pipeline installed on the seabed is capable of containing a pre-determined test pressure at an environmental temperature without bursting or collapse of the pipeline and evidence of leakage of the test water. The test pressure is usually related to the maximum operating pressure times a design factor specified in the pipeline design basis. While the application of a hydrotest strength test has been common practice during the past five decades, today’s technology developments’, realized in the past 3 decades, have significantly contributed to high levels reliability in the design, fabrication and installation processes. So, the question is warranted – can the high cost, critical path execution schedule delay and the environmental damage of the hydrotest be avoided? Can we replace the hydrotest, and with what? The paper describes the difficulties, schedule delays and likely costs entailed when carrying out a full-scale hydrotest and is considering an alternative approach to assessing the safety of the as-installed pipeline. It addresses the practical aspects of a hydrotest and discusses an alternative approach. While not compromising the safety of operating the as-installed pipeline, the alternative safety assessment is presented using existing quality of the design, manufacturing and installation technologies. The paper presents some examples for various circumstances.

To request a copy of the full paper please complete the application form.